Orofino Asbestos Cost Recovery

Judicial · FY2015 · — · Final Order With Specified Cost Recovery · 3600054913

Penalty
Cost recovery
Compliance action

Case

Case Number
10-2015-0131
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
Self-disclosure
N

Defendants (5)

Summary

On August 2, 2016, the U.S. District Court for the District of Idaho entered an ability-to-pay Consent Decree resolving liability and ordering payment of $523,000 in past costs for EPA?s removal actions at the Orofino Asbestos Superfund Site during 2008-2010. The asbestos contamination occurred when Owyhee Construction, a contractor of the Riverside Water and Sewer District, crushed concrete asbestos pipe and then disposed it as fill across several properties in Orofino, Idaho.