# Skytanking USA, Inc. (Chicago, IL) CAFO
> **Administrative - Formal** · FY2015 · — · Final Order With Penalty
## Case
- **Activity ID:** `3600093215`
- **Case Number:** 05-2015-7299
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Skytanking USA Inc. (complaint) (settlement)
## Summary

At all times Respondent operated a bulk oil Storage and distribution facility at 5401 Laramie Avenue, Chicago, IL. Respondent is subject to the spill prevention control and countermeasure plan regulations and is required to prepare and implement a SPCC Plan. Respondent is subject to the facility response plan regulations and is therefore required to submit and maintain an FRP plan in accordance with requirements. On January 6, 2011, Respondent notified the Illinois Emergency Management Agency that an oil spill had occurred at the truck loading area at the facility. On March 1, 2011, EPA received information indicating that strong fuel odors were emanating from the storm sewer adjacent to the facility at 4953 W. 63rd Street. On April 19, 2011 EPA conducted an inspection of the facility. At all times, Respondent?s SPCC Plan was dated July of 2005. On July 28, 2011 and December 28, 2011 EPA issued MATCO requests for information to evaluate MATCO?s and Respondent?s compliance with the CWA and oil pollution prevention regulations. On August 26, 2011 and February 3, 2012, MATCO submitted responses to these information requests. Count 1: After July of 2005, Respondent failed to complete a review and evaluation of the SPCC Plan at least once every five years, in violation of requirements. Count 2: From August of 2009 through August of 2011, Respondent failed to keep records of inspections, tests, discharge prevention briefings and training sessions with the SPCC Plan for a period of 

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*