> **Administrative - Formal** · FY2015 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `3600107330`
- **Case Number:** 02-2015-3105
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- L.P.C. & D., Inc. (settlement)
- Municipality of Guaynabo (settlement)
## Summary

COMPLIANCE ORDER ISSUED TO OWNER AND GENERAL CONTRACTOR FOR FAILURE TO OBTAIN NPDES PERMIT COVERAGE FOR ITS STORM WATER DISCHARGES FROM CONSTRUCTION ACTIVITIES INTO THE GUAYNABO RIVER.

---