# NECR Mine Site & UNC Mill Site AOC for Design
> **Administrative - Formal** · FY2015 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `3600134183`
- **Case Number:** 09-2015-2508
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- THE GENERAL ELECTRIC COMPANY (settlement)
- UNITED NUCLEAR CORPORATION (settlement)
## Summary

RESPONDENTS WILL RE-IMBURSE EPA PAST COSTS AND FUTURE COSTS AND WILL DESIGN THE REPOSITORY FOR THE NECR MINE WASTE.  THIS IS AN AMENDMENT TO THE ORIGINAL ORDER (09-2015-2500) TO ADD A SUPPLEMENTAL STATEMENT OF WORK FOR THE DESIGN AOC.

---