# Camden County Public Works
> **Administrative - Formal** · FY2015 · — · Final Order With Penalty
## Case
- **Activity ID:** `3600181409`
- **Case Number:** 02-2015-7921
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Camden County Public Works (complaint) (settlement)
## Summary

An EPA Contractor performed an inspection on January 22, 2014 and found a failure to perform annual line tightness test or perform monthly monitoring on pressurized piping, failure to conduct line tightness testing or use monthly monitoring on suction piping, and a failure to provide adequate line leak detection system for underground piping.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*