# Becton Dickinson Caribe Ltd.
> **Administrative - Formal** · FY2015 · — · Final Order With Penalty
## Case
- **Activity ID:** `3600363542`
- **Case Number:** 02-2015-3352
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Becton Dickinson Caribe Ltd. (complaint) (settlement)
## Summary

RESPONDENT FAILED TO  OBTAIN NPDES PERMIT COVERAGE FOR ITS STORM WATER DISCHARGES FROM THE FACILITY INTO A WATER OF THE UNITED STATES. A COUPLE OF MONTHS AFTER THE INSPECTION, THE FACILITY WAS CLOSED, AND NO FURTHER ACTIONS ARE REQUIRED. THIS PROCEEDING FOLLOWED 40 C.F.R. 22.18(B) -- SIMULTANEOUS COMMENCEMENT AND CONCLUSION OF THE ADMINISTRATIVE PENALTY.

---