# PG&E MERCURY EMERGENCY RESPONSE AOC
> **Administrative - Formal** · FY2016 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `3600661478`
- **Case Number:** 09-2016-2502
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- PACIFIC GAS AND ELECTRIC COMPANY (settlement)
## Summary

SETTLEMENT PROVIDES FOR THE PERFORMANCES OF A REMOVAL ACTION BY RESPONDENT AND THE PAYMENT OF RESPONSE COSTS INCURRED BY THE UNITED STATES AT OR IN CONNECTION WITH THE PG&E MERCURY EMERGENCY RESPONSE SITE.

---