# BISCAYNE NATIONAL PARK - CONVOY POINT  (FF)
> **Administrative - Formal** · FY2016 · — · Final Order With Penalty
## Case
- **Activity ID:** `3600736591`
- **Case Number:** 04-2016-9819
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- BISCAYNE NATIONAL PARK - CONVOY PLANT (complaint) (settlement)
## Summary

6/6/16 - EXPEDITED SETTLEMENT ISSUED, ASSESSING A PENALTY OF $630. 

VIOLATION:  INSTALLATION OF INADEQUATE SPILL PREVENTION EQUIPMENT IN A NEW TANK. IN VIOLATION OF 40 CFR SECTION 280.20(c)(1)(I).

VIOLATION:  FAILURE TO PROVIDE ADEQUATE LINE LEAK DETECTOR SYSTEM FOR UNDERGROUND PIPING. IN VIOLATION OF 40 CFR SECTION 280.44(a).

VIOLATION:  FAILURE TO PROVIDE ADEQUATE LINE TIGHTNESS TESTING SYTEM FOR UNDERGROUND PIPING SYSTEM. IN VIOLATION OF 40 CFR SECTION 280.44(b).

---