# BP Products North America Inc. (Whiting IN) CAFO
> **Administrative - Formal** · FY2016 · — · Final Order With Penalty
## Case
- **Activity ID:** `3600743351`
- **Case Number:** 05-2016-7375
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- BP Products North America Inc. (complaint) (settlement)
## Summary

Under the General Duty clause of the CAA, Section 112(r)(1), Respondent did not install a two-inch check valve on one end of the temporary quench line, as designed; Respondent did not develop a  Job Note  containing detailed instructions for the installation of the temporary quench line; Respondent did not create a Job Plan for the installation of the temporary quench line; Respondent's  management of change internal review process failed to determine whether the temporary quench line was properly installed; Respondent did not include key stakeholders affected by the installation of the temporary quench line; Respondent failed to design and maintain a safe facility taking such steps as are necessary to prevent accidental releases, in violation of the General Duty Clause at Section 112(r)(1) of the CAA.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*