# NextEra Energy Resources, LLC Chaves Solar Project
> **Administrative - Formal** · FY2016 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `3600744399`
- **Case Number:** 06-2016-1804
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- NextEra Energy Resources, LLC (settlement)
## Summary

The violation stems from two rain events of one quarter inch or greater at the site, which resulted in a discharge of pollutants from the site into waters of the United States in violation of Section 301 of the CWA.  Respondent did not submit a Notice of Intent (NOI) for permit coverage for its activities at the facility, and was not covered by a NPDES permit at the relevant times for the relevant activities.

---