# E. W. Johnson Company, Inc.
> **Administrative - Formal** · FY2017 · — · Final Order With Penalty
## Case
- **Activity ID:** `3600907202`
- **Case Number:** 06-2017-0909
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- E. W. Johnson Company, inc. (complaint) (settlement)
## Summary

On December 13, 2016, the EPA issued a Consent Agreement and Final Order to E.W. Johnson, Inc. for violations of RCRA.  During an investigation performed by EPA it was discovered that during the calendar years 2012 through 2015, E.W. Johnson?s facility generated and offered for transport and treatment the hazardous waste that exceeded the small quantity generator status, qualifying the facility to the large quantity generator status.  E.W. Johnson is ordered to pay a penalty of $57,192.00 and to establish compliance with the regulation.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*