← EPA enforcement cases

Norfolk Southern Railway Company

Administrative - Formal · FY2017 · — · Final Order With Specified Cost Recovery · 3600966100

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2017-2012
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On March 1, 2016, the Settling Party's freight train derailed at the Site. Two of four derailed train cars transporting ethanol began to leak as a consequence of the derailment. A propane tank car also derailed, but it was not compromised. The Settling Party undertook a removal action at the Site from March 2, 2016, to March 4, 2016. EPA incurred response costs pursuant to Section 104(a) of CERCLA, for its response activities performed at the Site, including assistance in and oversight of the removal action.

Source

Authoritative
EPA ECHO
Machine