# CRUIZERS 240
> **Administrative - Formal** · FY2017 · — · Final Order With Penalty
## Case
- **Activity ID:** `3601071265`
- **Case Number:** 04-2017-9819
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- CRUIZERS 240 (complaint) (settlement)
## Summary

6/8/17 - UST FIELD CITATION FOR EXPEDITED SETTLEMENT ISSUED, ASSESSING A PENALTY OF $580.

VIOLATION 1:  FAILURE TO INSPECT IMPRESSED CURRENT SYSTEMS EVERY 60 DAYS. IN VIOLATION OF 40 CFR SECTIN 280.31(c).

VIOLATION 2:  FAILURE TO PROVIDE ADEQUATE LINE LEAK DETECTOR SYSTEM FOR UNDERGROUND PIPING.  IN VIOLATION OF 40 CFR SECTION 280.44(a).

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*