# MCNAMARA MASONRY RESTORATION, INC.
> **Administrative - Formal** · FY2017 · — · Final Order With Penalty
## Case
- **Activity ID:** `3601126124`
- **Case Number:** 03-2017-0163
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- MCNAMARA MASONRY RESTORATION, INC. (complaint) (settlement)
## Summary

Respondent failed to: (1) provide The Lead-Safe Certified Guide to Renovate Right lead hazard information 
pamphlet: (2) post required lead work warning signs; (3) cover the ground with plastic sheeting or other 
disposable impermeable material; (4) retain records documenting compliance with work practice requirement: (5) obtain firm certification for renovations on Target Housing; and (6) ensure workers were certified. Under the terms of the CAFO, Respondent will pay a civil penalty in the amount of $5,144.00.  This Consent Agreement and Final Order initiates and concludes this matter.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*