← EPA enforcement cases

Accurate Builders & Developers of NJ

Administrative - Formal · FY2017 · — · Final Order With Penalty · 3601167548

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2017-3311
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

The Respondent gained coverage under the NJDEP Construction General Permit (CGP) to disturb approximately 15 acres of land at the Emerald Hills construction site. The Respondent failed to maintain stormwater BMPs including: failure to install and maintain sediment barriers; failure to maintain construction site entrances; failure to implement and maintain inlet protection; and failure to properly manage construction waste. These measures are required by the CGP and the Site Stormwater Pollution Prevention Plan. The penalty has been calculated at $15,000.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown