← EPA enforcement cases

GMD-Amador Project

Administrative - Formal · FY2018 · — · Unilateral Administrative Order Without Adjudication · 3601352455

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2018-1702
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

GMD Development NM, LLC, Respondent, owned or operated the Amador Project construction site, located in Las Cruces, Dona Ana County, New Mexico. Respondent failed to comply with the General Construction Permit. The violation was detected during a May 12, 2017 inspection conducted by NMED on behalf of EPA. EPA addressed violation with the issuance of an Administrative Order.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown