# City of Peekskill
> **Administrative - Formal** · FY2018 · — · Final Order With Penalty
## Case
- **Activity ID:** `3601390289`
- **Case Number:** 02-2018-3314
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- City of Peekskill (complaint) (settlement)
## Summary

This Consent Agreement and Final Order memorializes a settlement regarding Clean Water Act violations associated with the Respondent's Municipal Separate Storm Sewer System. The City has agreed to pay a civil cash penalty in the amount of $2,500 and will complete a Supplemental Environmental Project consisting of a porous pavement parking lot at a cost of $17,596.

---