← EPA enforcement cases

Rutlin Cranberry Company, Inc.

Administrative - Formal · FY2018 · — · — · 3601409689

Penalty
Cost recovery
Compliance action

Case

Case Number
05-2018-9967
Type
Administrative - Formal
Lead
EPA
Outcome
Multimedia
Self-disclosure
N

Defendants (1)

Summary

Rutlin, by 2020, must complete wetland restoration over 23.71 acres Rutlin must pay $25,000.00 within 30 days of Consent Agreement and Final Order (or March 26, 2018) 5.5 acre wetland creation/buffer contiguous w/ wetland restoration site as a Supplemental Environmental Project

Source

Authoritative
EPA ECHO
Machine