← EPA enforcement cases

Brooklyn Union Gas Co. d/b/a National Grid NY

Administrative - Formal · FY2018 · — · Final Order With Unspecified Cost Recovery · 3601449191

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2018-2003
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Unspecified Cost Recovery
Multimedia
Self-disclosure
N

Defendants (1)

Summary

Under this AOC, the Respondent will: 1) construct the Fulton Wall after the design is completed under the Fulton Wall Design UAO; 2) remove MGP-related contamination at a) the Canal-side Property outside the footprint of the RH-034 Tank, following and contingent upon the City's acquisition of the Canal-side Property and demolition of structures thereon, b) at the Park Property if the RH-034 Tank is sited at the Canal-side Property, and c) if EPA selects the Park Property for the location of the RH-034 Tank, at the Park Property outside the footprint of the tank; and 3) develop plans for and provide a temporary swimming pool or pools; and, 4) if the City acquires the Canal-side Property, develop plans for and permanently replace the pool and impacted park areas of the Park Property.

Source

Authoritative
EPA ECHO
Machine