Kaplan Companies

Administrative - Formal · FY2018 · — · Final Order With Penalty · 3601502066

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2018-3401
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

This administrative penalty order is being issued in conjunction with an administrative order on consent, CWA-02-2018-3031, which requires the Respondent to implement a company-wide stormwater compliance program at its construction sites. The $100,000 penalty amount is based on NJPDES Construction General Permit violations at four (4) construction sites in New Jersey.