← EPA enforcement cases

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION

Administrative - Formal · FY2018 · — · Final Order With Penalty · 3601605791

Penalty
Cost recovery
Compliance action

Case

Case Number
03-2018-0032
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

EPA AND THE PENNSYLVANIA DEPARTMENT OF TRANSPORTATION (PENNDOT) HAVE AGREED TO SETTLE A MULTI-SITE CONSTRUCTION-RELATED STORMWATER CASE. THE CASE RESOLVES 191 VIOLATIONS FOR FAILURE TO PERFORM SELF-INSPECTIONS AT CONSTRUCTION SITES AND AT LEAST 18 VIOLATIONS FOR FAILURE TO IMPLEMENT BEST MANAGEMENT PRACTICES. THE SETTLEMENT, ENCOMPASSED IN A CONSENT AGREEMENT AND FINAL ORDER (FILED 09/28/18) AS WELL AS AN ADMINISTRATIVE ORDER ON CONSENT (FILED 08/30/18), REQUIRE PENNDOT TO PAY A PENALTY OF $100,000, IMPLEMENT A COMPLIANCE MANAGEMENT PROGRAM AND IMPLEMENT AND ENVIRONMENTAL BENEFICAL PRORAM IN THE CODORUS CREEK WATERSHED. THIS CASE ADVANCES THE ENVIRONMENTAL OBJECTIVE OF THE CLEAN WATER ACT IN PROTECTING THE NATION'S WATERWAYS FROM POLLUTANTS THAT HARM HUMAN HEALTH AND THE ENVIRONMENT.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown