← EPA enforcement cases

Pure Design & Build

Administrative - Formal · FY2019 · — · Final Order With Penalty · 3601756602

Penalty
Cost recovery
Compliance action

Case

Case Number
10-2019-0052
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On May 30, 2019, Region 10 issued an Expedited Settlement Agreement and Final Order to Pure Design & Build located in Boise, Idaho, for violations of the RRP Rule occurring in Boise, Idaho. The EPA alleged that Pure Design & Build failed to become RRP firm certified prior to performing renovation work on pre-1978 residential properties as required by the RRP Rule. Respondent agreed to settle and pay a penalty amount of $1,000.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown