# LHV Precast Inc.
> **Administrative - Formal** · FY2019 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `3601871801`
- **Case Number:** 02-2019-3031
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- LHV Precast Inc. (settlement)
## Summary

Respondent operates a precast concrete facility. On May 10, 2019, EPA conducted an inspection and identified that the Facility conducts industrial activity regulated under 40 C.F.R. 122.26 and discharges stormwater associated with industrial activity, including runoff from concrete mix loading area, to a tributary to the Hudson River via an on-site storm sewer system and outfall. At the time of the inspection, the Facility did not have coverage under a SPDES Permit. This Order serves to require the Facility to obtain SPDES permit coverage for the unpermitted stormwater discharges associated with the industrial operations.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*