← EPA enforcement cases

JSK ELECTRICAL & CONSTRUCTION LLC

Administrative - Formal · FY2019 · — · Final Order With Penalty · 3601902467

Penalty
Cost recovery
Compliance action

Case

Case Number
07-2019-0206
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

RESPONDENT FAILED TO COMPLY WITH RRP REQUIREMENTS INCLUDING THE REQUIREMENT TO OBTAIN INITIAL FIRM CERTIFICATION; TO ASSIGN A CERTIFIED RENOVATOR; POST SIGNS DEFINING THE WORK AREA AND WARN OCCUPANTS AND OTHER PERSONS TO REMAIN OUTSIDE THE WORK AREA; TO CLOSE DOORS AND WINDOWS IN THE AREA, AND TO COVER THE FLOOR WITH IMPERMEABLE MATERIAL.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown