← EPA enforcement cases

Eco Services Operations-Baytown Plant-RMP ESA

Administrative - Formal · FY2019 · — · Final Order With Penalty · 3601902895

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2019-3340
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

From September 17-19, 2018, an authorized representative of the EPA conducted a compliance inspection of the subject facility (Respondent) to determine compliance with the Risk Management Plan (RMP) regulations promulgated at 40 CFR Part 68 under Section 112(r) of the Act, 42 USC 74 !2(r). EPA found that the Respondent had violated regulations implementing Section 112(r) of the Act, 42 USC 7412(r) by failing to comply with the regulations as noted in the final order.