← EPA enforcement cases

Paint Over Rust Products, Inc. f/k/a Absolute Coatings, Inc.

Administrative - Formal · FY2019 · — · Final Order With Penalty · 3601967069

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2019-4201
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On September 25, 2018 the US EPA conducted an on-site inspection to determine whether the facility was in compliance with the chemical reporting requirements of the Emergency Planning and Community Right-To-Know Act (EPCRA), Section 313 - Toxics Release Inventory (TRI) program. The following issues were identified: late or non-reporting for Diisocyanates for years 2015, 2016, and 2017; and 1,2,4-Trimethylbenzene for 2017.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown