# BWAY CORP - APO/CAFO
> **Administrative - Formal** · FY2019 · — · Final Order With Penalty
## Case
- **Activity ID:** `3601992445`
- **Case Number:** 05-2019-5057
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- BWAY CORP (complaint) (settlement)
## Summary

EPA identified emissions escaping a coating line (Litho Line #4) using an infrared camera during an inspection.  Litho Line #4 is subject to the requirements of NESHAP KKKK as a permanent total enclosure (PTE).  By failing to capture all emissions generated at Litho Line #4, BWAY failed to maintain the PTE, a violation of NESHAP KKKK.  This case has a concurrent Consent Agreement and Final Order that includes a penalty of $140,000.
This ACO requires BWAY to add new ductwork to expand ducting to the exit of the oven at Litho Line #4, install a new blower to route emissions from Litho Line #4 to an existing thermal oxidizer, and modify the duct header connection to the existing thermal oxidizer.  Following these modifications, BWAY will conduct a performance test to confirm that Litho Line #4 meets the requirements of a PTE.  These modifications to Litho Line #4 will reduce emissions by 26 tons per year, and addresses the violations set forth in the FOV issued to BWAY on December 22, 2017.

---