Blue Mountain Midstream-Chisholm Trail Gas Complex-RMP AOC-FY2020

Administrative - Formal · FY2019 · — · Final Order No Penalty · 3602025789

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2019-3364
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On June 11, 2019, EPA conducted an onsite CAA 40 CFR Part 68 and Section 112(r) compliance evaluation of the facility. Based on the PHA conducted on September 27, 2018, Respondent failed to promptly address the team's findings and recommendations in a timely manner, in violation of 40 CFR 68.67(e). Based on the documentation provided, Respondent failed to document a record that each employee involved in operating a process had received and understood the training required, in violation of 40 CFR 68.71(c).