ASAOC for RD at River Mile 7 West Project Area: Arkema and Bayer CropScience

Administrative - Formal · FY2020 · — · — · 3602123432

Penalty
Cost recovery
Compliance action

Case

Case Number
10-2020-0054
Type
Administrative - Formal
Lead
EPA
Outcome
Multimedia
Self-disclosure
N

Defendants (3)

Summary

This Settlement provides for the performance of 100% Remedial Design of the River Mile 7 West Project Area and the payment by Respondents of certain response costs incurred by the EPA, the Oregon Department of Environmental Quality, and the Tribal Governments at or in connection with the Work conducted under this Settlement, related to the selected remedy for the in-river portion of the Portland Harbor Superfund Site (the Site).