# Essex Water District et al.
> **Administrative - Formal** · FY2020 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `3602135857`
- **Case Number:** 02-2020-8009
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Essex Supervisor (settlement)
- Essex Town Board (settlement)
- Essex Water District (settlement)
## Summary

System must construct water treatment plant for compliance with Stage 2 DBPR according to revised compliance schedule.

---