# FENOC_GRADEL
> **Judicial** · FY2018 · — · —
## Case
- **Activity ID:** `3602245810`
- **Case Number:** 05-2018-1099
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** —
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- First Energy Nuclear Operating Company (complaint) (settlement)
- George Gradel Company, Inc (complaint) (settlement)
## Summary

Complaint alleges that Defendants violated CWA section 301(a) by discharging dredged or fill material and/or controlling and directing the discharge of dredged or fill material into waters of the US at the Davis Besse Firing Range Site located at 818 Front Street, Port Clinton, Ohio (the  Site ) and more fully described in the Complaint, without a permit issued by the United States Department of the Army Corps of Engineers (the  Corps )

---