Molina LLC dba Molina Handyman & Construction

Administrative - Formal · FY2020 · — · Final Order With Penalty · 3602251579

Penalty
Cost recovery
Compliance action

Case

Case Number
10-2020-0145
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On September 9, 2020, Region 10 issued an expedited settlement agreement and Final Order to Molina LLC dba Molina Handyman & Construction (?Molina LLC?) for a violation of the RRP Rule occurring in Burley, Idaho. The EPA Region 10 alleged that Molina LLC failed to become RRP firm certified prior to performing renovation work on a pre-1978 residential property as required by the RRP Rule. Respondent agreed to settle and pay a penalty amount of $200.