Chloe Construction Company, LLC

Administrative - Formal · FY2020 · — · Final Order With Penalty · 3602299114

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2020-9279
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

Based on an EPA investigation conducted in response to a referral from New York City Department of Health, Respondent violated the Renovation Repair, and Painting Rule when it conducted renovations in NYC by failing to obtain firm certification, failing to assign a certified renovator, failing to provide the owner of building with Renovate Right pamphlet, and failing to retain records documenting compliance with the Rule.