# Midcoast Pipelines-Zybach Cryo Plant-Briscoe, TX-RMP ESA-FY2021
> **Administrative - Formal** · FY2021 · — · Final Order With Penalty
## Case
- **Activity ID:** `3602439555`
- **Case Number:** 06-2021-3321
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Midcoast Pipelines/Texas Gathering LP (complaint) (settlement)
## Summary

On July11, 2019, EPA conducted an inspection of the facility to determine compliance with 40 CFR Part 68. Respondent violated 68.71(b) by failing to provide refresher training at least every three years to employees working in the RMP covered process.

---