← EPA enforcement cases

Hess Corp.- Tioga Gas Plant

Administrative - Formal · FY2021 · — · Final Order With Penalty · 3602490214

Penalty
Cost recovery
Compliance action

Case

Case Number
08-2021-0068
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

October 7/2015 EPA conducted an SPCC inspection and documented SPCC Plan deficiencies, numerous technical deficiencies, including lack of secondary containment, and failure to submit an FRP for the facility.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown