← EPA enforcement cases

FOUR RIVERS NUCLEAR PARTNERSHIP, LLC (PADUCAH GASEOUS DIFFUSION PLANT)

Administrative - Formal · FY2021 · — · Final Order With Penalty · 3602702866

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2021-0200
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

4/8/2021 - CONSENT AGREEMENT AND FINAL ORDER ISSUED ASSESSING A PENALTY OF $2,986.00.00. PENALTY DUE WITHIN 30 DAYS. ALLEGED VIOLATIONS: BASED ON EPA?S COMPLIANCE MONITORING INVESTIGATION CONDUCTED ON APRIL 17-18, 2018, THE EPA ALLEGES THAT THE RESPONDENT VIOLATED 40 C.F.R. PART 68, THE CODIFIED RULES GOVERNING THE ACT?S CHEMICAL ACCIDENT PREVENTION PROVISIONS AND SECTION 112(R) OF THE ACT, 42 U.S.C. ? 7412(R), WHEN IT: A. FAILED TO DOCUMENT THE NAMES OR POSITIONS OF THE PEOPLE RESPONSIBLE FOR IMPLEMENTING INDIVIDUAL REQUIREMENTS OF 40 C.F.R. PART 68 AND DEFINE THE LINES OF AUTHORITY THROUGH AN ORGANIZATION CHART OR SIMILAR DOCUMENT AS REQUIRED BY 40 C.F.R. ? 68.15(C); AND B. FAILED TO REVIEW OPERATING PROCEDURES AS OFTEN AS NECESSARY TO ASSURE THAT THEY REFLECT CURRENT OPERATING PRACTICE, INCLUDING CHANGES THAT RESULT FROM CHANGES IN PROCESS CHEMICALS, TECHNOLOGY, AND EQUIPMENT, AND CHANGES TO STATIONARY SOURCES AND FAILED TO CERTIFY ANNUALLY THAT THESE OPERATING PROCEDURES ARE CURRENT AND ACCURATE AS REQUIRED BY 40 C.F.R. ? 68.69(C).

Source

Authoritative
EPA ECHO
Machine