# Ballard CD with P4 Production
> **Judicial** · FY2021 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `3602721021`
- **Case Number:** 10-2021-0137
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- P4 Production (complaint) (settlement)
## Summary

The United States in its complaint seeks, inter alia: (1) reimbursement of costs
incurred by EPA and the Department of Justice (?DOJ?) for response actions at the Ballard Mine
Superfund Site in Caribou County, Idaho (?Site?), together with accrued interest; and
(2) performance of response actions by Defendant P4 Production, L.L.C. (?Settling Defendant?)
at the Site consistent with the National Contingency Plan, 40 C.F.R. Part 300 (?NCP?).

---