# Lamb Trust
> **Administrative - Formal** · FY2021 · — · Final Order No Penalty
## Case
- **Activity ID:** `3602722807`
- **Case Number:** 08-2021-0104
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Karl Lamb and David Lamb (complaint) (settlement)
## Summary

On July 29, 2019, Karl and David Lamb (Respondents') used a track hoe to excavate materials from the Duchesne River and floodplain, as well as to partially construct a diversion channel that ran onto the neighboring parcel held in trust for the Ute Indian Tribe. Respondents' activities were undertaken without a permit from the U.S. Army Corps of Engineers.

---