# ERWIN PLANT, LLC
> **Administrative - Formal** · FY2021 · — · Final Order With Penalty
## Case
- **Activity ID:** `3602819443`
- **Case Number:** 04-2021-3200
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- ERWIN PLANT, LLC (complaint) (settlement)
## Summary

SEPTEMBER 7, 2021 - CONSENT AGREEMENT AND FINAL ORDER ISSUED: On November 21, 2019, an authorized agent of the EPA Region 4 conducted an inspection at the Facility pursuant to Section 15 of TSCA, 15 U.S.C. ? 2614, to determine the Facility's
compliance with the PCB regulations. the EPA alleges that Respondent  failed to:

a. Conduct and/or document inspections checking for leaks at least once every 30 days for all PCB Transformers in storage.

b. Have a proper storage area with an adequate roof, walls, and non-porous floor with curbing for all the PCB Transformers. 

c. Mark all the storage areas used to store PCB Transformers, except the area where the #29 transformer was being stored, with the appropriate PCB label.

d. Mark all the PCB Transformers, with a date when they were removed from service for disposal. 

e. Dispose all the PCB Transformers, within 1-year from the date the PCB Transformers were determined to be PCB Waste. 

f. Notify the EPA of PCB Waste activities by filling out and submitting EPA Form 7710-53.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*