# Neale Gas Processing Plant-Merryville,LA-RMP ESA-FY2022
> **Administrative - Formal** · FY2022 · — · Final Order With Penalty
## Case
- **Activity ID:** `3602996192`
- **Case Number:** 06-2022-3325
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Neale Gas Processing (complaint) (settlement)
## Summary

On April 5, 2021, EPA's Risk Management Program Reporting Center sent a letter to Respondent, notifying Respondent of its failure to update the Risk Management Plan on file with the EPA for its facility located in Dallas, Texas. EPA 's review indicated that the update for the facility was not submitted by the required due date of February 26, 2021, a violation of 40 CFR 68.190.

---