DPC Industries-Sweetwater,TX-RMP CAFO-FY2022

Administrative - Formal · FY2022 · — · Final Order With Penalty · 3603040980

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2022-3324
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On July 26, 2021, there was an incident at the Facility that resulted in an accidental release of chlorine. Subsequent to EPA's review, on December 3, 2021, the EPA sent Respondent a Notice of Potential Violation and Opportunity to Confer letter. EPA determined Respondent failed to perform inspections and tests on process equipment at a frequency consistent with applicable good engineering practices pursuant to 40 CFR 68.73(d)(2), and as required by 40 CFR 68.12(d)(3).