← EPA enforcement cases

City of Joplin

Administrative - Formal · FY2022 · — · Final Order No Penalty · 3603198961

Penalty
Cost recovery
Compliance action

Case

Case Number
07-2022-0015
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

The City of Joplin operates the Turkey Creek Wastewater Treatment Plant, which has repeatedly land-applied biosolids with zinc and/or cadmium concentrations that exceeded regulatory limits. On one occasion, crops were harvested within thirty days of biosolids application, also a violation of the biosolids regulations. The EPA and the City of Joplin have entered into an agreement to implement a new operating procedure for the land application of biosolids that will prevent future violations of applicable ceiling concentrations.