# RED HILL UTILITY, LLC
> **Administrative - Formal** · FY2022 · — · Final Order No Penalty
## Case
- **Activity ID:** `3603242328`
- **Case Number:** 03-2022-0018
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- RED HILL UTILITY, LLC (settlement)
## Summary

On May 22, 2023, the Division Director of ECAD signed an Amended Administrative Order on Consent (AAOC) for work to be performed under Sections 309(a) of the Clean Water Act (CWA), 33 U.S.C. 1319(a), amending the original Administrative Order on Consent signed on May 25, 2022.  Under the AAOC, Respondent has agreed to provide EPA a Corrective Action Plan ( CAP ) within 60 days which includes the following:  a) A plan and schedule for the construction of a new sewer line (the  Sewer Line ) along Puddledock Road from the Red Hill Facility to tie in with the Prince George collection system, approximately one mile from the Facility at an existing pump station located at the Puddledock Place Apartments, which plan and schedule shall include any ancillary upgrades and improvements as may be required by Prince George County; b) A plan and schedule for removal and closure of the existing wastewater treatment facility in accordance with closure requirements of VPDES Permit No. VA0028258, which shall take effect once the Sewer Line becomes operational; c) A plan for operation and maintenance of the Sewer Line.  Premised on Red Hill?s intent to transfer the Sewer Line to Prince George County, Red Hill shall also develop a plan and schedule for contacting Prince George County regarding utility conveyance, and a firm process for entering into an agreement with Prince George County regarding the operation and maintenance of the Sewer Line; d) An interim plan to maintain the existing wastew

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*