# Niagara Mohawk Power Corporation et al.
> **Administrative - Formal** · FY2022 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `3603304043`
- **Case Number:** 02-2022-2016
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- General Electric Company (settlement)
- Niagara Mohawk Power Corporation (settlement)
## Summary

Parties will perform deconstruction and monitoring with EPA oversight at the Hudson Falls Powerhouse and the Allen Mill Site. EPA's cost will be reimbursed.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*