← EPA enforcement cases

CALHOUN COMMERCIAL CONSTRUCTION, LLC

Administrative - Formal · FY2022 · — · Final Order With Penalty · 3603334718

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2022-0006
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

8/8/2022 - EXPEDITED SETTLEMENT AGREEMENT ISSUED ASSESSING A PENALTY OF $5,883. PENALTY DUE WITHIN 15 DAYS. ALLEGED VIOLATIONS: BASED ON INFORMATION OBTAINED FROM THE BARTOW COUNTY BUILDING DEPARTMENT AND INFORMATION OBTAINED FROM THE RESPONDENT VIA TELEPHONE AND ELECTRONIC MAIL, THE EPA ALLEGES THAT RESPONDENT VIOLATED SECTION 112 OF THE CAA, 42 U.S.C. ? 7412, AND 40 C.F.R. PART 61, SUBPART M. SPECIFICALLY, THE EPA ALLEGES THE RESPONDENT FAILED TO CONDUCT A THOROUGH INSPECTION FOR ASBESTOS-CONTAINING MATERIALS PRIOR TO BEGINNING DEMOLITION ACTIVITY, AS REQUIRED BY 40 C.F.R. ? 61.145(A), AT TEXACO LOCATED AT 71 OLD GRASSDALE ROAD, N.E. IN CARTERSVILLE, GEORGIA 30121 (THE FACILITY). EPA ALSO ALLEGES THE RESPONDENT FAILED TO PROVIDE WRITTEN NOTICE TO THE GEORGIA ENVIRONMENTAL PROTECTION DIVISION (EPD) 10 WORKING DAYS PRIOR TO BEGINNING THE DEMOLITION ACTIVITY, AS REQUIRED BY 40 C.F.R. ? 61.145(B). NO NOTICE WAS PROVIDED TO THE EPD. DEMOLITION COMMENCED AT THE FACILITY ON OR AROUND NOVEMBER 17, 2021.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown