# General Electric Company
> **Administrative - Formal** · FY2022 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `3603363844`
- **Case Number:** 02-2022-2011
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- General Electric Company (settlement)
## Summary

The Order directs the Respondent to implement remedial action, operation & maintenance, and monitoring of the remedy selected in the March 2013 Record of Decision (ROD) for Operable Unit (OU) 1 and in the September 30, 2019 ROD for OU 2 at the Site. Under the Order, the Respondent is directed to undertake the groundwater remedies for the three areas of the Site, Areas 1, 2, and 3, which contain an approximately 7 mile-long contaminant plume. Respondent completed the remedial design of these components under a prior administrative consent order. The work in the Order is valued at approximately $4,300,000.

On September 22, 2023, a letter agreement was signed between EPA and the Respondent in which the Respondent agrees to pay EPA oversight costs associated with the Cayuga County Groundwater Contamination Site remedy for Areas 1-3, which work is being performed under Administrative Order for Remedial Action, Index No. CERCLA-02-2022-2011 (UAO).

---