← EPA enforcement cases

University Park Sewer Benefit District et al.

Administrative - Formal · FY2022 · — · Final Order With Penalty · 3603373302

Penalty
Cost recovery
Compliance action

Case

Case Number
07-2022-0081
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

The University Park Sewer Benefit District and Riley County Public Works Department operate a publicly-owned treatment works near Tuttle Creek Lake that has repeatedly exceeded applicable NPDES permit limits for biochemical oxygen demand, total suspended solids, ammonia as nitrogen, and E. coli. In addition, EPA inspectors observed deficiencies in how the facility laboratory operated during a May 2021 inspection. EPA Region 7 and Respondents have entered into an administrative penalty order and agreed to a $1,750 penalty.