# Champion WD 2, 4 & 5
> **Administrative - Formal** · FY2023 · — · Final Order No Penalty
## Case
- **Activity ID:** `3603420368`
- **Case Number:** 02-2023-8003
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Champion WD 2, 4, & 5 (settlement)
## Summary

SDWA-02-2023-8003 is an administrative order (AO) that supersedes SDWA-02-2022-8016. This AO incorporates the corrective action plan submitted by the town into an enforceable schedule to achieve compliance with the Stage 2 DBPR.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*