EPA conducted an on-site inspection and compliance evaluation of the Facility from January 31, 2022, to February 14, 2022, to determine  compliance with Section 112(r) of the CAA, 42 USC 7412(r), and 40 CFR Part 68. EPA identified six violations of the RMP rules.

---