# Energy Transfer-Geismar Fractionation-Geismar,LA-RMP CAFO-FY2023
> **Administrative - Formal** · FY2023 · — · Final Order With Penalty
## Case
- **Activity ID:** `3603474549`
- **Case Number:** 06-2023-3313
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Energy Transfer CC NGLs LLC (complaint) (settlement)
## Summary

EPA conducted an inspection of the Facility from August 08, 2022 to August I I, 2022, to determine compliance with the CAA Section 112(r) and 40 CFR Part 68. On October 04, 2022, the EPA sent Respondent a Notice of Potential Violation and Opportunity to Confer letter. On October 15, 2022, the EPA responded to the documentation and information received from Respondent as a result of the opportunity to confer. EPA determined four findings of violation.

---